Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Attendees

Notes

  • Brandon Hippe:

    • Eric showing good receive down to -85 dBm in pluto with MF-based clock recovery. With traditional clock recovery algorithm, even at -50 dBm we are getting 191/200 bits recovered correctly. -70 to -80dBm ish, drops off even faster

  • David Burnett

    • Coordinating EWSN submission, now delayed to Jan 7

    • Finishing tapeout due February

  • Titan Yuan

    • Q1 seat but mostly working on control systems

  • Sara Faour

    • Arranged special meeting about zero helper data concept

    • Three methods: power off time, voltage fluxuation, and power on ramp rate

      • Time control more feasible on SCuM because precision requirements of this timer is not very high